Drone video from the entire construction of the highway "Europe" - A6 (LOT-1) from Dragoman to Kalotina.
The route of this part of the highway is already formed along its entire length. A road overpass-east is being built in Dragoman, and the west must be completed. The subways under the lower lane have been built and the traffic has been transferred to them. The construction of their other halves is forthcoming. The eco-product (bear product) is completely built and humus has already been laid on it. The construction of the railway overpass continues, which seems to improve the turn of the railway line. After its construction, the temporary overpass, on which trains are currently moving to and from Serbia, will be removed.
14.5 km from km 1 + 000 to km 15 + 500 with gauge A-25.5 m and design speed 100 km / h. It is planned to build 10 large facilities - 4 overpasses, 2 agricultural underpasses, 2 underpasses, 1 overpass and 1 bridge.
On June 17, 2019, a contract for construction supervision was signed with DZZD "Nadzor Kalotina - SOP" and the deadline for implementation is 910 days. The first sod was made on February 13, 2020.
Video: "Europe" Highway A6 construction (Dragoman - Kalotina) - Lot 1
Video Format: 4k
Date: 19.07.2022
Music: Bensound
Redistribution is NOT allowed without explicit permit. Any reproductions or distributions of content elsewhere is a violation of the license under which this video is available on the YouTube platform
The route of this part of the highway is already formed along its entire length. A road overpass-east is being built in Dragoman, and the west must be completed. The subways under the lower lane have been built and the traffic has been transferred to them. The construction of their other halves is forthcoming. The eco-product (bear product) is completely built and humus has already been laid on it. The construction of the railway overpass continues, which seems to improve the turn of the railway line. After its construction, the temporary overpass, on which trains are currently moving to and from Serbia, will be removed.
14.5 km from km 1 + 000 to km 15 + 500 with gauge A-25.5 m and design speed 100 km / h. It is planned to build 10 large facilities - 4 overpasses, 2 agricultural underpasses, 2 underpasses, 1 overpass and 1 bridge.
On June 17, 2019, a contract for construction supervision was signed with DZZD "Nadzor Kalotina - SOP" and the deadline for implementation is 910 days. The first sod was made on February 13, 2020.
Video: "Europe" Highway A6 construction (Dragoman - Kalotina) - Lot 1
Video Format: 4k
Date: 19.07.2022